Array ( [id] => 164642 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州学校项目教育地块一期竣工 下月迎新 [editor] => (编辑)叶虹 [has_thumb] => 1 [created] => 2020-08-15 09:11:06 [createdby] => 10025 [createdip] => 112.54.37.33 [published] => 2020-08-15 09:11:06 [publishedby] => 10025 [modified] => 2020-08-15 10:15:33 [modifiedby] => 10092 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 389 [virtual_pv] => 376 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

12日上午,福州学校项目部内,一面面青年突击队的红旗静静伫立,挂在墙上的照片里,展示的是5月举办的“大干100天,确保福州学校项目教育地块一期顺利交付”誓师大会暨劳动竞赛时的热闹场景。3个多月过去,照片中“躲”在红旗“海洋”后的栋栋被绿网笼罩的楼体,早已换上新装。

记者从市城投集团下属市建发集团获悉,经过300多天的全时段“战斗”,福州学校完成首轮冲刺目标——总建筑面积6.8万平方米的教育地块一期顺利竣工,具备交付条件。下个月,这所坐落在三江口片区的新学堂就将迎来首批新生。

匠心打磨 造百年工程

沿刚建成不久的上董一路前行,道路右侧,白色半圆形拱门敞开怀抱,这里就是福州学校小学部的主入口。入口中央,3棵特选荔枝树与地面的清华文化浮雕图案相映成趣,带着“励志”的美好寓意,更寄托着对学生学业硕果累累的期待。

往里看去,“躲”在院内的白墙、拱廊探出“头”来。入口处,一个个戴着安全帽的身影进进出出,全力为项目交付展开最后冲刺。

12日上午,在市建发集团副总工陈旭丹的带领下,记者提前“入园”探访。首先映入眼帘的,是白墙黛瓦的4层教学楼,外侧脚手架上,施工人员在各自的“自留地”忙碌。“这些工人都是好手艺,专门进行墙体柱体线角精细打磨、再次外墙涂刷,实现品质提升。”陈旭丹说,目前,教育地块一期的整体施工基本完成,按精品工程目标,品质提升的“临门一脚”正加快收尾。

伴着教学楼的施工“协奏曲”,沿楼梯而上,崭新的教室静待迎接新生,与之比邻的宽敞走廊让人眼前一亮。

据了解,楼内走廊宽度被提升为4米,还添置了一个个延伸出去的“小阳台”,给学生们提供更舒适、通透的通行及活动空间。分设在一、二层的风雨连廊,把4栋教学楼连成整体,串起学生的主要活动空间,即使下雨天,各楼栋间也畅通无阻。

走出教学楼,在院落中,还有颜值颇高的10栋宿舍楼、“食堂+风雨操场”、室外运动跑道的惊喜,作为教育地块一期的“主角团”,它们将和教学楼同期交付。

“这照明灯垂直度不行,赶紧重装。”“游园”途中,陈旭丹带领的品质小分队成员还不忘“找茬”:通往风雨操场沿线的墙面地灯安装粗糙、路沿石边角顺直度偏差、卫生清理不够……按“当下改”原则,整改都在陆续展开,确保交付时干干净净、清清爽爽。

精心配置 建活力新校

以“水木清华”为主线,精心点缀的清华文化图案,伴着灵活多变的院落布局,白墙黛瓦的建筑,西式特色的拱廊、拱券,加上外廊植入的青砖墙体,让这所新校尽情展现兼容并包的美。组团“绽放”的背后,还有许多巧妙心思。

随处可见的绿,从小学部主入口的大广场上就开始延展。一棵特选朴树伫立场内,形态古雅、别致,树景与建筑相得益彰。往校园内走,一个个活动平台、檐口、墙面等处,也被立体绿化的绿意填满,还有福建山樱花、紫玉兰、蓝花楹等为校园添色。

在教学楼“包裹”的内庭,一棵冠大荫浓的老榕静静伫立,配上相互错落的庭院空间,打造别具一格的“古榕书院”。“这棵树可是学校‘元老’。”陈旭丹说,这棵榕树本就“住”在原拆迁场地内,在校园设计时被特意保留,既有福州“榕城”寓意,也体现了“十年树木,百年树人”的教育理念,今后,会成为朗朗读书声的最好陪伴。

除了看得见的巧思,在园路下,还“藏”着看不见的巧思。考虑到项目是填方场地,为让学校“底子”更稳更扎实,也给后期维护管养提供便利,原本“各自为政”的给水、雨水、污水、电力等室外管线统一“入廊”,通过管廊方式,有效减少沉降通病。

带着教育地块一期竣工的喜悦与收获,紧盯2021年项目整体建成的目标,陈旭丹带领的“超越梦想项目部”开始新一轮攻坚:体育地块加快推进结构施工、教育地块二期11月力争封顶……


来源:福州新闻网
编辑:叶虹 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/thumb\/10001\/202008\/27505b9b8861ac872329a402c9c43527.jpeg@w377_h282.jpeg","id":"1844502"}] [url] => /p/164642.html [all_pv] => 389 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 教学楼 [1] => 地块 [2] => 福州 [3] => 教育 [4] => 交付 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 161806 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/161806.html [wapUrl] => http://m.fztvapp.zohi.tv/p/161806.html [published_timestamp] => 1594693615 [published] => 1594693615 [pv] => 99 [virtual_pv] => 455 [all_pv] => 99 [title] => 福州学校项目建设展开冲刺 下月教育地块一期竣工交付 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/202007/c532fb6ebd526db47a5517e2dd029868.jpeg@w582_h437.jpeg ) [1] => Array ( [relateid] => 69957 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/69957.html [wapUrl] => http://m.fztvapp.zohi.tv/p/69957.html [published_timestamp] => 1550973433 [published] => 1550973433 [pv] => 432 [virtual_pv] => 434 [all_pv] => 432 [title] => 晋安多个教育项目有进展 福州七中扩容工程4月交付使用 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201902/3ea4432cd8bdef610a65d2d56991d47d.jpeg ) [2] => Array ( [relateid] => 147614 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/147614.html [wapUrl] => http://m.fztvapp.zohi.tv/p/147614.html [published_timestamp] => 1582610548 [published] => 1582610548 [pv] => 148 [virtual_pv] => 378 [all_pv] => 148 [title] => 福州公布多个地块控规调整公告 涉开元寺北侧地块 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/202002/23778487547f041774cdeaca61eb5546.png ) [3] => Array ( [relateid] => 162288 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/162288.html [wapUrl] => http://m.fztvapp.zohi.tv/p/162288.html [published_timestamp] => 1595157579 [published] => 1595157579 [pv] => 120 [virtual_pv] => 409 [all_pv] => 120 [title] => 福州学校(暂名)部分教学楼下月交付 周边两条新路基本建成 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/202007/5afa25e59cb8fdc87f82df43b63f8176.jpeg ) [4] => Array ( [relateid] => 81690 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/81690.html [wapUrl] => http://m.fztvapp.zohi.tv/p/81690.html [published_timestamp] => 1555566482 [published] => 1555566482 [pv] => 483 [virtual_pv] => 465 [all_pv] => 483 [title] => 福州出让9幅地块 鼓楼区两地块首次采用新方式拍卖 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/c7b91f26782d271991cc021871ad6586.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/thumb/10001/202008/27505b9b8861ac872329a402c9c43527.jpeg@w377_h282.jpeg ) 1

福州学校项目教育地块一期竣工 下月迎新

2020-08-15 09:11   福视悦动  

12日上午,福州学校项目部内,一面面青年突击队的红旗静静伫立,挂在墙上的照片里,展示的是5月举办的“大干100天,确保福州学校项目教育地块一期顺利交付”誓师大会暨劳动竞赛时的热闹场景。3个多月过去,照片中“躲”在红旗“海洋”后的栋栋被绿网笼罩的楼体,早已换上新装。

记者从市城投集团下属市建发集团获悉,经过300多天的全时段“战斗”,福州学校完成首轮冲刺目标——总建筑面积6.8万平方米的教育地块一期顺利竣工,具备交付条件。下个月,这所坐落在三江口片区的新学堂就将迎来首批新生。

匠心打磨 造百年工程

沿刚建成不久的上董一路前行,道路右侧,白色半圆形拱门敞开怀抱,这里就是福州学校小学部的主入口。入口中央,3棵特选荔枝树与地面的清华文化浮雕图案相映成趣,带着“励志”的美好寓意,更寄托着对学生学业硕果累累的期待。

往里看去,“躲”在院内的白墙、拱廊探出“头”来。入口处,一个个戴着安全帽的身影进进出出,全力为项目交付展开最后冲刺。

12日上午,在市建发集团副总工陈旭丹的带领下,记者提前“入园”探访。首先映入眼帘的,是白墙黛瓦的4层教学楼,外侧脚手架上,施工人员在各自的“自留地”忙碌。“这些工人都是好手艺,专门进行墙体柱体线角精细打磨、再次外墙涂刷,实现品质提升。”陈旭丹说,目前,教育地块一期的整体施工基本完成,按精品工程目标,品质提升的“临门一脚”正加快收尾。

伴着教学楼的施工“协奏曲”,沿楼梯而上,崭新的教室静待迎接新生,与之比邻的宽敞走廊让人眼前一亮。

据了解,楼内走廊宽度被提升为4米,还添置了一个个延伸出去的“小阳台”,给学生们提供更舒适、通透的通行及活动空间。分设在一、二层的风雨连廊,把4栋教学楼连成整体,串起学生的主要活动空间,即使下雨天,各楼栋间也畅通无阻。

走出教学楼,在院落中,还有颜值颇高的10栋宿舍楼、“食堂+风雨操场”、室外运动跑道的惊喜,作为教育地块一期的“主角团”,它们将和教学楼同期交付。

“这照明灯垂直度不行,赶紧重装。”“游园”途中,陈旭丹带领的品质小分队成员还不忘“找茬”:通往风雨操场沿线的墙面地灯安装粗糙、路沿石边角顺直度偏差、卫生清理不够……按“当下改”原则,整改都在陆续展开,确保交付时干干净净、清清爽爽。

精心配置 建活力新校

以“水木清华”为主线,精心点缀的清华文化图案,伴着灵活多变的院落布局,白墙黛瓦的建筑,西式特色的拱廊、拱券,加上外廊植入的青砖墙体,让这所新校尽情展现兼容并包的美。组团“绽放”的背后,还有许多巧妙心思。

随处可见的绿,从小学部主入口的大广场上就开始延展。一棵特选朴树伫立场内,形态古雅、别致,树景与建筑相得益彰。往校园内走,一个个活动平台、檐口、墙面等处,也被立体绿化的绿意填满,还有福建山樱花、紫玉兰、蓝花楹等为校园添色。

在教学楼“包裹”的内庭,一棵冠大荫浓的老榕静静伫立,配上相互错落的庭院空间,打造别具一格的“古榕书院”。“这棵树可是学校‘元老’。”陈旭丹说,这棵榕树本就“住”在原拆迁场地内,在校园设计时被特意保留,既有福州“榕城”寓意,也体现了“十年树木,百年树人”的教育理念,今后,会成为朗朗读书声的最好陪伴。

除了看得见的巧思,在园路下,还“藏”着看不见的巧思。考虑到项目是填方场地,为让学校“底子”更稳更扎实,也给后期维护管养提供便利,原本“各自为政”的给水、雨水、污水、电力等室外管线统一“入廊”,通过管廊方式,有效减少沉降通病。

带着教育地块一期竣工的喜悦与收获,紧盯2021年项目整体建成的目标,陈旭丹带领的“超越梦想项目部”开始新一轮攻坚:体育地块加快推进结构施工、教育地块二期11月力争封顶……


来源:福州新闻网