Array ( [id] => 166968 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 工业路提升改造顺利推进 上浦人行天桥月底拆除 [editor] => (编辑)强婕宁 [has_thumb] => 1 [created] => 2020-09-10 09:31:05 [createdby] => 10056 [createdip] => 112.54.37.33 [published] => 2020-09-10 09:31:05 [publishedby] => 10056 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 484 [virtual_pv] => 482 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

记者9日从市城乡建设局获悉,工业路(上浦路—杨桥路)提升改造工程在全力做好文明施工课题的同时,正进行管线迁改及桩基等基础施工。按计划,本月底,上浦人行天桥将拆除,工业路(乌山西路至上浦路口段)也开始围挡,展开桩基施工,整体工程力争2022年上半年建成。

9日上午,记者来到该工程工业路杨桥路口围挡处,这里正进行过街雨水顶管施工,围挡外,车流、人流有序通行。

市城乡建总该项目负责人林捷介绍,工业路(上浦路—杨桥路)提升改造工程起于上浦路金山大桥桥头,向北延伸,终于杨桥路(连接在建工业北路延伸段),全长3.66公里(工业路改造长度2.5公里,上浦路改造长度0.73公里,乌山西路改造长度0.43公里),宽40米,是条与西二环平行的南北向快速通道。

作为治堵核心,工程将建起“2+3”的“主线连续流”组合。其中,“2”指上浦路口、乌山路口2座立交,“3”指3座高架,分别为连接上浦路和金山大桥的上浦路高架、上跨上浦路与乌山路的工业乌山高架及起于杨桥路附近,与在建工业北路延伸段相接的工业杨桥高架。

“工业路上浦路口处即将开始桩基施工,由于标高限制,上浦人行天桥会在月底先行拆除。”林捷介绍说,本月底,该工程的新动向还包括工业路(乌山西路至上浦路口)的围挡施工,将占用路中间的机动车道,进行桩基作业。

此外,位于苏宁广场西侧,横跨工业路和大庆河的祥坂人行天桥(暂名)建设也同步展开。目前,全长约60米的天桥桩基施工基本完成,预计年底可开放通行。

作为地处城市中心区的治堵工程,为最大程度减少对市民出行和城市环境影响,该项目的文明施工也做实做细。在施工时间内,除净车出场外,喷淋系统全线作业,雾炮机也在现场随时待命,避免扬尘。针对施工期间产生的废水,会通过围挡基座下设置的导流槽集中收集、沉淀后再按规定处理。

按计划,该项目将力争在2022年上半年整体建成,作为与西二环平行的“西2.5环”,可有效分流西二环的交通压力。“西2.5环”启动,也为远期金山大道快速化改造奠定基础,助力城区西面交通大提速。



来源:福州新闻网
编辑:强婕宁 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202009\/bbe7077e74665ec2fd93f2c604a7754f.jpeg","id":"1856230"}] [url] => /p/166968.html [all_pv] => 484 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 浦路 [1] => 施工 [2] => 工业 [3] => 桩基 [4] => 围挡 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 131940 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/131940.html [wapUrl] => http://m.fztvapp.zohi.tv/p/131940.html [published_timestamp] => 1574831048 [published] => 1574831048 [pv] => 128 [virtual_pv] => 420 [all_pv] => 128 [title] => 工业路(上浦路—杨桥路) 提升改造工程可研报告获批 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201911/b0e616586cdf6ba4a370a7d74f39aec8.jpeg ) [1] => Array ( [relateid] => 146678 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/146678.html [wapUrl] => http://m.fztvapp.zohi.tv/p/146678.html [published_timestamp] => 1581995545 [published] => 1581995545 [pv] => 212 [virtual_pv] => 469 [all_pv] => 212 [title] => 福州前横路改造工程桩基施工快速推进 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/202002/1f8e224161255f746061ba9302b0ac89.jpeg ) [2] => Array ( [relateid] => 91383 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/91383.html [wapUrl] => http://m.fztvapp.zohi.tv/p/91383.html [published_timestamp] => 1559276196 [published] => 1559276196 [pv] => 453 [virtual_pv] => 369 [all_pv] => 453 [title] => 出行请注意!地铁施工,福州这些地方近期将围挡! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/6e5af0d6939b5c70ce88fd3b040137ae.jpeg ) [3] => Array ( [relateid] => 112911 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/112911.html [wapUrl] => http://m.fztvapp.zohi.tv/p/112911.html [published_timestamp] => 1567646399 [published] => 1567646399 [pv] => 235 [virtual_pv] => 454 [all_pv] => 235 [title] => 福州将集中整治围挡和施工场地 国庆前力争焕新貌 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201909/7fe5f29d67644e00d2818110f4734384.jpeg ) [4] => Array ( [relateid] => 156866 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/156866.html [wapUrl] => http://m.fztvapp.zohi.tv/p/156866.html [published_timestamp] => 1589854583 [published] => 1589854583 [pv] => 211 [virtual_pv] => 387 [all_pv] => 211 [title] => “西2.5环”!福州工业路将有大变化! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/202005/62501b57caf7ee732f473bf59d6d49dd.png ) ) [article_thumb] => http://www.zohi.tv/a/10001/202009/bbe7077e74665ec2fd93f2c604a7754f.jpeg ) 1

工业路提升改造顺利推进 上浦人行天桥月底拆除

2020-09-10 09:31   福视悦动  

记者9日从市城乡建设局获悉,工业路(上浦路—杨桥路)提升改造工程在全力做好文明施工课题的同时,正进行管线迁改及桩基等基础施工。按计划,本月底,上浦人行天桥将拆除,工业路(乌山西路至上浦路口段)也开始围挡,展开桩基施工,整体工程力争2022年上半年建成。

9日上午,记者来到该工程工业路杨桥路口围挡处,这里正进行过街雨水顶管施工,围挡外,车流、人流有序通行。

市城乡建总该项目负责人林捷介绍,工业路(上浦路—杨桥路)提升改造工程起于上浦路金山大桥桥头,向北延伸,终于杨桥路(连接在建工业北路延伸段),全长3.66公里(工业路改造长度2.5公里,上浦路改造长度0.73公里,乌山西路改造长度0.43公里),宽40米,是条与西二环平行的南北向快速通道。

作为治堵核心,工程将建起“2+3”的“主线连续流”组合。其中,“2”指上浦路口、乌山路口2座立交,“3”指3座高架,分别为连接上浦路和金山大桥的上浦路高架、上跨上浦路与乌山路的工业乌山高架及起于杨桥路附近,与在建工业北路延伸段相接的工业杨桥高架。

“工业路上浦路口处即将开始桩基施工,由于标高限制,上浦人行天桥会在月底先行拆除。”林捷介绍说,本月底,该工程的新动向还包括工业路(乌山西路至上浦路口)的围挡施工,将占用路中间的机动车道,进行桩基作业。

此外,位于苏宁广场西侧,横跨工业路和大庆河的祥坂人行天桥(暂名)建设也同步展开。目前,全长约60米的天桥桩基施工基本完成,预计年底可开放通行。

作为地处城市中心区的治堵工程,为最大程度减少对市民出行和城市环境影响,该项目的文明施工也做实做细。在施工时间内,除净车出场外,喷淋系统全线作业,雾炮机也在现场随时待命,避免扬尘。针对施工期间产生的废水,会通过围挡基座下设置的导流槽集中收集、沉淀后再按规定处理。

按计划,该项目将力争在2022年上半年整体建成,作为与西二环平行的“西2.5环”,可有效分流西二环的交通压力。“西2.5环”启动,也为远期金山大道快速化改造奠定基础,助力城区西面交通大提速。