Array ( [id] => 171444 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 永泰马洋大桥28日起封闭施工 [editor] => (编辑)叶虹 [has_thumb] => 1 [created] => 2020-10-28 17:09:42 [createdby] => 10025 [createdip] => 112.54.37.33 [published] => 2020-10-28 17:09:42 [publishedby] => 10025 [modified] => 2020-10-29 18:16:56 [modifiedby] => 10054 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 430 [virtual_pv] => 407 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => [content] =>

建于1998年的马洋大桥,由于桥面窄小且荷载等级低,已不能满足目前的交通需求。为此,永泰县将于28日起,对马洋大桥进行封闭施工改造。

马洋大桥位于永泰县城峰镇,旧桥全长200米,上部为钢筋混凝土简支T梁结构,下部为U型桥台。

规划新建的大桥全长207.2m,桥面宽度为26m,为双向四车道,包含机动车道、人行道、非机动车道、隔离护栏等,目前正在进行桥梁拆除前的准备工作。

马洋大桥改造工程技术负责人张国亮:“本项目目前处于临时驻地建设预制梁场的建设阶段,整个合同建设工期是18个月,拟建桥梁上部结构采用(3×30)m+(3×30)m预应力混凝土连续箱梁+14m现浇钢筋混凝土空心板,下部采用柱式墩桩基础、U型桥台扩大基础。”

为保障施工期间道路交通有序、安全、畅通,从10月28日起至施工结束(工期约18个月),马洋大桥将实行交通管制,禁止机动车、非机动车和行人通行。过往车辆及行人可绕道城关大桥(塔山大桥)、刘岐大桥及石圳大桥。

马洋大桥改造工程技术负责人张国亮:“我们计划10月28日开始在南北两桥头进行围挡封闭施工,11月9日开始拆桥工作,计划年前完成桥梁桩基部分的施工 。”


来源:大美永泰
编辑:叶虹 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/thumb\/10001\/202010\/697c7feeb892eca20c239eaec4920dec.jpeg@w766_h575.jpeg","id":"1880464"}] [url] => /p/171444.html [all_pv] => 430 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 大桥 [1] => 马洋 [2] => 施工 [3] => 28 [4] => 混凝土 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 112554 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/112554.html [wapUrl] => http://m.fztvapp.zohi.tv/p/112554.html [published_timestamp] => 1567507724 [published] => 1567507724 [pv] => 824 [virtual_pv] => 454 [all_pv] => 824 [title] => 新建福厦高铁乌龙江特大桥进入承台及墩柱施工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201909/9c299157796c53ca4fa8bcf8784e75d8.jpeg ) [1] => Array ( [relateid] => 128745 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/128745.html [wapUrl] => http://m.fztvapp.zohi.tv/p/128745.html [published_timestamp] => 1573610283 [published] => 1573610283 [pv] => 46 [virtual_pv] => 408 [all_pv] => 46 [title] => 永泰黄埔大桥通车 全省首座大跨径钢筋混凝土连续拱桥 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201911/315719e906432e08798d30ef2af6b247.jpeg ) [2] => Array ( [relateid] => 112590 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/112590.html [wapUrl] => http://m.fztvapp.zohi.tv/p/112590.html [published_timestamp] => 1567509070 [published] => 1567509070 [pv] => 255 [virtual_pv] => 471 [all_pv] => 255 [title] => 新建福厦高铁乌龙江特大桥进入承台及墩柱施工 预计2021年实现贯通 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201909/53709559ed388d29367a596c2f0f914f.jpg ) [3] => Array ( [relateid] => 69846 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/69846.html [wapUrl] => http://m.fztvapp.zohi.tv/p/69846.html [published_timestamp] => 1550909158 [published] => 1550909158 [pv] => 655 [virtual_pv] => 378 [all_pv] => 655 [title] => 橘园洲大桥西桥头互通立交正全力施工 年底通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201902/1d6bf2bdf18f78df181c8106aa15ecdc.jpeg ) [4] => Array ( [relateid] => 160322 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/160322.html [wapUrl] => http://m.fztvapp.zohi.tv/p/160322.html [published_timestamp] => 1593135914 [published] => 1593135914 [pv] => 151 [virtual_pv] => 448 [all_pv] => 151 [title] => 新洪山桥“造腿” 老洪塘大桥腾位 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/202006/53ca42fa7050cd5a817e731b25f99049.jpeg@w646_h485.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/thumb/10001/202010/697c7feeb892eca20c239eaec4920dec.jpeg@w766_h575.jpeg ) 1

永泰马洋大桥28日起封闭施工

2020-10-28 17:09   福视悦动  

建于1998年的马洋大桥,由于桥面窄小且荷载等级低,已不能满足目前的交通需求。为此,永泰县将于28日起,对马洋大桥进行封闭施工改造。

马洋大桥位于永泰县城峰镇,旧桥全长200米,上部为钢筋混凝土简支T梁结构,下部为U型桥台。

规划新建的大桥全长207.2m,桥面宽度为26m,为双向四车道,包含机动车道、人行道、非机动车道、隔离护栏等,目前正在进行桥梁拆除前的准备工作。

马洋大桥改造工程技术负责人张国亮:“本项目目前处于临时驻地建设预制梁场的建设阶段,整个合同建设工期是18个月,拟建桥梁上部结构采用(3×30)m+(3×30)m预应力混凝土连续箱梁+14m现浇钢筋混凝土空心板,下部采用柱式墩桩基础、U型桥台扩大基础。”

为保障施工期间道路交通有序、安全、畅通,从10月28日起至施工结束(工期约18个月),马洋大桥将实行交通管制,禁止机动车、非机动车和行人通行。过往车辆及行人可绕道城关大桥(塔山大桥)、刘岐大桥及石圳大桥。

马洋大桥改造工程技术负责人张国亮:“我们计划10月28日开始在南北两桥头进行围挡封闭施工,11月9日开始拆桥工作,计划年前完成桥梁桩基部分的施工 。”


来源:大美永泰