Array ( [id] => 175550 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州市轨道交通1号线二期工程顺利通过专家评审 [editor] => (编辑)翁彬冰 [has_thumb] => 1 [created] => 2020-12-16 17:15:59 [createdby] => 10022 [createdip] => 112.54.37.33 [published] => 2020-12-16 17:15:59 [publishedby] => 10022 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 518 [virtual_pv] => 476 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => [content] =>

2020年12月13日至16日,福州市轨道交通1号线二期工程暨与一期工程贯通初期运营前安全评估会在福州召开。本次会议参会单位包括上海市交通运输行业协会、评估专家,福州市人民政府、市仓山区人民政府、市直有关单位部门、市地铁集团、上海隧道院及勘察、设计、施工、设备、监理及监测等相关单位。

(图为福州市轨道交通1号线二期专家评估会现场)

本次安全评估首次会议上,专家组观看了1号线二期专题片,听取了本工程建设情况综合报告、运营情况综合报告等,详细介绍了安全评估要求。随后进行现场踏勘测试,共分五组同时进行,分别为总体组、土建组、设备一组、设备二组、运营组。

专家组通过现场检查工程总体设计、安装工艺质量、各系统功能及联动功能等,并审阅了综合联调报告、系统联动测试报告、预检查整改情况汇总材料等工程技术资料。检查期间,分公司福州1号线二期项目部完全响应并积极配合,指派专业技术人员全程配合并解答专家提出的问题。

最后专家组通过分组交流讨论并形成专家组评估意见,通过与各参建单位进行反馈交流,最终形成统一意见。专家组对本次安全评估给予高度评价,充分肯定了本工程各参建单位的工作。最后专家组组长宣读专家评估意见,市地铁集团发言,市政府领导讲话,宣布福州市轨道交通1号线二期工程暨与一期工程贯通初期运营前安全评估会顺利通过。

评审的顺利通过标志着,至此福州市轨道交通1号线二期已完全具备初期运营条件,项目部将积极做好开通前各项保障工作,为月底正式开通初期运营保驾护航。福州市轨道交通1号线二期是连接福州主城区、三江口片区的重要交通通道,还将与在建6号线实现换乘,实现与滨海新城的连通,打通福州市“东进南下、沿江向海”的轨道交通线。


来源:中铁电化城铁福建
编辑:翁彬冰 责编:庄颖

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202012\/98e22f48b95c6470aac4358fe795ab33.jpeg","id":"1900454"}] [url] => /p/175550.html [all_pv] => 518 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 号线 [1] => 福州市 [2] => 评估 [3] => 专家组 [4] => 二期 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 162806 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/162806.html [wapUrl] => http://m.fztvapp.zohi.tv/p/162806.html [published_timestamp] => 1595670839 [published] => 1595670839 [pv] => 90 [virtual_pv] => 376 [all_pv] => 90 [title] => 福州地铁1号线一期接受“转正”评估 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/202007/51b41bdc490e9a29816e129df8199e3c.jpeg ) [1] => Array ( [relateid] => 119622 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/119622.html [wapUrl] => http://m.fztvapp.zohi.tv/p/119622.html [published_timestamp] => 1570086889 [published] => 1570086889 [pv] => 546 [virtual_pv] => 370 [all_pv] => 546 [title] => 福州地铁1号线二期、4号线、5号线、6号线又有新进展 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201910/7b8f87d3ab1d2138a011470ac1a71368.jpeg ) [2] => Array ( [relateid] => 154372 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/154372.html [wapUrl] => http://m.fztvapp.zohi.tv/p/154372.html [published_timestamp] => 1587641566 [published] => 1587641566 [pv] => 332 [virtual_pv] => 403 [all_pv] => 332 [title] => 福州地铁1号线二期全线轨道贯通 力争年底前实现初期运营 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/202004/2384ff5f152e7e93b935dcf439390685.jpg@w849_h478.jpg ) [3] => Array ( [relateid] => 154258 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/154258.html [wapUrl] => http://m.fztvapp.zohi.tv/p/154258.html [published_timestamp] => 1587554300 [published] => 1587554300 [pv] => 155 [virtual_pv] => 441 [all_pv] => 155 [title] => 刚刚!1号线二期全线“轨通”! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/202004/e21f46ae31d18e66e820cb5837c87b0a.jpeg ) [4] => Array ( [relateid] => 117636 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/117636.html [wapUrl] => http://m.fztvapp.zohi.tv/p/117636.html [published_timestamp] => 1569376358 [published] => 1569376358 [pv] => 151 [virtual_pv] => 408 [all_pv] => 151 [title] => 福州地铁1号线二期车站全封顶 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201909/0a91509373c28a6190ea693049ebcb20.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/202012/98e22f48b95c6470aac4358fe795ab33.jpeg ) 1

福州市轨道交通1号线二期工程顺利通过专家评审

2020-12-16 17:15   福视悦动  

2020年12月13日至16日,福州市轨道交通1号线二期工程暨与一期工程贯通初期运营前安全评估会在福州召开。本次会议参会单位包括上海市交通运输行业协会、评估专家,福州市人民政府、市仓山区人民政府、市直有关单位部门、市地铁集团、上海隧道院及勘察、设计、施工、设备、监理及监测等相关单位。

(图为福州市轨道交通1号线二期专家评估会现场)

本次安全评估首次会议上,专家组观看了1号线二期专题片,听取了本工程建设情况综合报告、运营情况综合报告等,详细介绍了安全评估要求。随后进行现场踏勘测试,共分五组同时进行,分别为总体组、土建组、设备一组、设备二组、运营组。

专家组通过现场检查工程总体设计、安装工艺质量、各系统功能及联动功能等,并审阅了综合联调报告、系统联动测试报告、预检查整改情况汇总材料等工程技术资料。检查期间,分公司福州1号线二期项目部完全响应并积极配合,指派专业技术人员全程配合并解答专家提出的问题。

最后专家组通过分组交流讨论并形成专家组评估意见,通过与各参建单位进行反馈交流,最终形成统一意见。专家组对本次安全评估给予高度评价,充分肯定了本工程各参建单位的工作。最后专家组组长宣读专家评估意见,市地铁集团发言,市政府领导讲话,宣布福州市轨道交通1号线二期工程暨与一期工程贯通初期运营前安全评估会顺利通过。

评审的顺利通过标志着,至此福州市轨道交通1号线二期已完全具备初期运营条件,项目部将积极做好开通前各项保障工作,为月底正式开通初期运营保驾护航。福州市轨道交通1号线二期是连接福州主城区、三江口片区的重要交通通道,还将与在建6号线实现换乘,实现与滨海新城的连通,打通福州市“东进南下、沿江向海”的轨道交通线。


来源:中铁电化城铁福建
编辑:翁彬冰 责编:庄颖