Array ( [id] => 234734 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福厦高铁最大跨度连续刚构拱桥拱肋顺利合龙 [editor] => (编辑)黄国伟 [has_thumb] => 1 [created] => 2022-01-12 12:41:54 [createdby] => 10270 [createdip] => 112.54.37.33 [published] => 2022-01-12 12:41:56 [publishedby] => 10270 [modified] => 2022-01-12 12:43:00 [modifiedby] => 10054 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 710 [virtual_pv] => 383 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => 017e4c959fa7c0010000e84b39da3fcf [cdv_type] => 1 [content] =>

11日,福厦高铁6标泉州湾跨海大桥主跨160米连续刚构拱桥拱肋顺利合龙。 中交二航局 供图

1月11日,随着最后一节拱肋准确对位,由中交二航局承建的全线最大跨度连续刚构拱桥——福厦高铁6标泉州湾跨海大桥主跨160米连续刚构拱桥拱肋顺利合龙。

该连续刚构拱桥位于泉州台商投资区琅山村附近,横跨交通繁忙的泉州绕城高速,全长313.6米,采用梁拱组合结构,共含26节拱肋,设置18组双吊杆。拱肋节段采用支架法安装,单个节段最重达38吨,拱肋最高处离地面达60多米,且支架跨度大,梁底净空小,对施工安全管控提出了更高要求。

“此次合龙的拱肋,节段重、体积大、灵活性差,且受泉州湾季风及上跨高速影响,施工技术难度大。为此,我们多次组织召开专题会议,电脑模拟各节段吊装工况,由测量人员全程进行测量,多次精调,最终对接精度、线形及高程控制均满足设计高要求,顺利完成合龙施工。”项目常务副经理刘福星表示。

据悉,2022年是福厦铁路6标的全面收官之年,目前项目部正进行无砟轨道铺设,预计明年6标段施工将全部完成。福厦高铁建成通车后,福州、厦门两地将实现“一小时生活圈”,福建6市将实现“高铁进京”。


来源:东南网
编辑:黄国伟 责编:庄颖

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202201\/ec446f4da8297b10ced32fdd478ed5c7.jpeg","id":"2177436"}] [url] => /p/234734.html [all_pv] => 710 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 福厦 [1] => 合龙 [2] => 刚构 [3] => 泉州 [4] => 拱桥 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( ) [article_thumb] => https://www.zohi.tv/a/10001/202201/ec446f4da8297b10ced32fdd478ed5c7.jpeg ) 1

福厦高铁最大跨度连续刚构拱桥拱肋顺利合龙

2022-01-12 12:41   福视悦动  

11日,福厦高铁6标泉州湾跨海大桥主跨160米连续刚构拱桥拱肋顺利合龙。 中交二航局 供图

1月11日,随着最后一节拱肋准确对位,由中交二航局承建的全线最大跨度连续刚构拱桥——福厦高铁6标泉州湾跨海大桥主跨160米连续刚构拱桥拱肋顺利合龙。

该连续刚构拱桥位于泉州台商投资区琅山村附近,横跨交通繁忙的泉州绕城高速,全长313.6米,采用梁拱组合结构,共含26节拱肋,设置18组双吊杆。拱肋节段采用支架法安装,单个节段最重达38吨,拱肋最高处离地面达60多米,且支架跨度大,梁底净空小,对施工安全管控提出了更高要求。

“此次合龙的拱肋,节段重、体积大、灵活性差,且受泉州湾季风及上跨高速影响,施工技术难度大。为此,我们多次组织召开专题会议,电脑模拟各节段吊装工况,由测量人员全程进行测量,多次精调,最终对接精度、线形及高程控制均满足设计高要求,顺利完成合龙施工。”项目常务副经理刘福星表示。

据悉,2022年是福厦铁路6标的全面收官之年,目前项目部正进行无砟轨道铺设,预计明年6标段施工将全部完成。福厦高铁建成通车后,福州、厦门两地将实现“一小时生活圈”,福建6市将实现“高铁进京”。